Library
A double storey reference library to stock books, archival and
resource material for in-depth study and research work on history
and theology, film and video and musical rendering of sacred hymns
contained in Guru Granth.
Structural work complete
Flooring work complete
Roofing work in complete
False ceiling work complete
External stone cladding Completed
Cost of construction = Rs.3.73 Crores
|
Changing
Exhibit Gallery
Changing Exhibit Gallery for arranging short duration / solo exhibitions
by individual artists / organizations.
Structural work complete
Roofing work complete
False ceiling work complete
Flooring work Completed
External stone cladding Completed
Cost of construction= Rs.3.20 Crores
|
|
Auditorium
400 seat capacity auditorium for lectures, seminars, symposia,
discourses and visual performances.
Structural work complete
Roofing work Complete
False ceiling work Complete
Flooring work Completed
External stone cladding work Completed
Cost of construction = Rs.5.97 Crores
|
Cafeteria
Cafeteria for visitors to take refreshment.
Structural work complete
Roofing work complete
False ceiling work Complete
Flooring work Complete
External stone cladding work Complete
Cost of construction = Rs.6.49 Crores
|

|
Heritage
Building
High walled heritage building with a ramp to walk while looking
at the heritage panorama projection through most modern state-of-the-art
multimedia techniques.
Structural work complete
Roofing work complete
False ceiling work in progress
Flooring work complete
External stone cladding work complete
Cost of construction = Rs.10.62 Crore
|
Media
Exhibit building
Media Exhibit building with five petal flowered roofs. The building
has halls and galleries on two floors to describe and depict the
event of history.
Structural work complete
Finishing works in progress
Cost of construction = Rs.12.52 Crores (Building Part)
|
Permanent
Exhibit building
Permanent Exhibit building with sloping roofs. The building has
large halls and galleries where exhibits shall be shown with latest
multimedia techniques. The highest point is approx. 46m (151 feet)
above the adjoining water body level giving the effect of a fort
emanating from a sandcliff.
Structural work complete
Finishing works in progress
Stone cladding work complete
Cost of construction = Rs.29.23 Crores
|

|
Landscaping
Landscaping in an area of 40 acres in the vicinity of the complex
shall be carried out.
Total complex
cost
= Rs. 157.93 crores
Expenditure
incurred till date (i.e. 31.07.2008) = Rs. 135.18 crores |

|