Cost of the Project

Summary of Construction Cost Rs (Crores) $ (Million)
1. Cost of Building Works 157.93 39.48
2. Cost of Exhibit Implementation 66.07 16.52
Total 224.00 56.00

 

Detail of Construction Cost : Rs ( Crores) $ (Million)
1. Main building presently under construction by M/s L&T Ltd 115.00 28.75
2. Pedestrian bridge already constructed 3.19 0.80
3. Transmission line and 66 KV Sub-station 2.56 0.64
4. Boundary Wall and 6 nos. gates 2.40 0.60
5. Horticulture Works 2.03 0.51
6. Other miscellaneous works 32.75 8.18
(These cost do not include the costs towards escalation) Total 157.93 39.48

Detail of Cost of Exhibits for Permanent Exhibit Galleries :

Cost of Exhibits

66.07 16.52

Details of Cost : Building component wise :

Note: Cost are inclusive of Site development, landscaping and Site Services.

Target dates of completion

 -Building Construction                                                 30.12.2008                                          31.03.2009

- Exhibits Phase-I                                                         April,2009

Exhibit Phase-II                                                            March,2010  

Expenditure incurred upto July 31, 2008:

1 On Construction part Rs. 123.94 Crores
2 Architect's Fees Rs. 11.24 Crores
3 Exhibit Conceptual design Rs. 06.01 Crores
Total Rs. 141.19 Crores


Funds required :

Year-wise

1st Stage : Requirement to finish Building Rs. 50 Crores = $ 10 million
2nd Stage : Requirement to Exhibit Rs. 100 Crores = $ 20 million

The Govt. of India and Govt of Punjab have agreed for financial assistance of the matching amount as received through the public contribution.